Dillinger Hütte | Germany

A new ladder track was required to provide more parking tracks in the steel plant. At the same time, the layout of the dead end tracks were optimised and the efficiency of the whole depot improved by installing the Frauscher Advanced Counter FAdCi in combination with the wheel sensor RSR180. With the implementation of the Frauscher Diagnostic System FDS, the overall maintenance costs can be significantly reduced.

Hanning & Kahl implemented 16 power operated, locally controlled points (EOW). A SIL3 proven control ensures safe, flexible and efficient operation. The Frauscher Axle Counter FAdCi in combination with the wheel sensor RSR180 guarantees reliable train detection, while Frauscher Diagnostic System FDS provides diagnostic data to the higher level control system.

Thanks to the FDS which allows collection of data all over the system, the maintenance staff is now provided with diagnostic tools and a virtual track representation of the entire depot area. Irregularities and failures can be detected in advance before coming to expensive breakdowns. With the condition-based maintenance replacing scheduled maintenance, the overall cost can be significantly reduced.

Functional modularity

The FAdC provides reset options, counting head information, counting head control functionality and comprehensive diagnostic facilities.

Optimise maintenance

Analysis of diagnostic data provided by FDS allows condition-based maintenance and preventive measures.

Project details
Operator
AG der Dillinger Hüttenwerke
Country or region
Germany
Partner
Hanning & Kahl GmbH
Segment
Industrial & Mining
Axle Counting
Frauscher Advanced Counter FAdCi, Frauscher Diagnostic System FDS
Wheel Detection
Wheel Sensor RSR180
Application
Track vacancy detection
Year
2012
Counting Head
34
Similar projects

This might also interest you

Frauscher Train Detection Metro Warsaw

Metro Warsaw | Poland

Metro Warsaw was looking for an alternative to track circuits for the line M2, to increase the availability of public transport by using reliable signalling technology. In the end, the operator even decided to replace the existing track circuits on line M1 with the Frauscher Axle Counter ACS200.

Edmonton Metro Line | Canada

The Edmonton Metro Line was experiencing significant issues with its newly installed Communications Based Train Control (CBTC) signalling system, which did not perform to the operator‘s expectations. The city was forced to run an incomplete schedule with reduced train speed and frequency which negatively affected commuters and the city of Edmonton in general. Finally in 2019, the operator decided to install a new system in cooperation with Frauscher.

Kokkola | Finland

Frauscher supplied one of Finland’s busiest railway lines with new Axle Counters. The line was extended from a single to a double track section and Mipro was looking for a solution which can interface with their interlocking system in an efficient and cost effective way. Other important criteria was a minimum maintenance requirement and outdoor equipment which can cope with the harsh environmental conditions in Finland.