Increasing Availability at Adra Yard | India
Train DetectionIndia

Increasing Availability at Adra Yard

Operator
Indian Railways - South Eastern Railway
Country
India
Partner
MRT
Segment
Main & Regional Line
Application
Track Vacancy Detection
Products
RSR180, FAdC®
Year
2022
Scope of project
139 counting heads, 97 track sections

Adra Yard belongs to the Southeastern Railway Zone of Indian Railways and is in West Bengal. Initially the yard was equipped with track circuits and there was a requirement to get them replaced with the Frauscher Advanced Counter FAdC®. This project is one of Frauscher’s esteemed Indian Railway Projects with a coverage of 139 counting heads and 97 track sections.

In this project, the FAdC® is placed in the Central Location as well as in three different end cabins. All four locations are connected in ring structure with redundant path of optical fibre cable for communication. Both the Frauscher Diagnostic System FDS are placed in Central Location and configured to connect to the rail network for remote diagnostic. The vital output of all track sections is in Central Location which is further connected to the Electronic Interlocking. Reset of all track sections can be carried out in Central Location.

The Frauscher Advanced Counter FAdC® is highly flexible regarding design and architecture. The Wheel Sensor RSR180 was also utilised, being rated IP68 protection class (waterproof) which means it is immune to floods, moisture or water. Due to the adverse weather conditions in this area, the wheel sensor’s ability to withstand such conditions is particularly useful.

Easy and cost-effective integration

Greater cost saving due to distributed architecture and lower maintenance requirement.

Increasing availability

Greater uptime and availability due to resistance to adverse weather.

Similar Projects
This might also interest you
1/5
Train Detection, ServicesIndia

Sini - Chandil Railway Line

The Sini-Chandil railway line is a crucial rail connection located in the state of Jharkhand, which lies in the eastern coastal region of India. This railway line holds significant strategic importance for the entire region, and now incorporates Frauscher solutions, including the Frauscher Advanced Counter FAdC®, Wheel Sensor RSR180 and the Frauscher Insights applications Diagnostics and Motion.
Train DetectionUnited States of America

Tracking Trains in Houston

Houston MetroRail (METRO for short) is comprised of three light-rail lines covering 22 miles. Two-car, low-floor trainsets are powered by overhead catenary and operated on a mix of rail types, including embedded, grooved, concrete, and ballasted track. Harsh weather conditions such as extreme heat, humidity, and storms with heavy rains causing floods are typical for Houston. Combined with the variable track structure this caused significant malfunctions of the wheel sensors of METRO’s signalling system.
Train DetectionUnited States of America

Charlotte Area Transit System (CATS) Supplementing Audio Frequency Track Circuits with Axle Counters

At the Charlotte Area Transit System, frequent false red signal overruns resulted when electromagnetic interference caused “bobbing” of the line’s audio frequency track circuits. The Frauscher Advanced Counter FAdC® was subsequently considered as an alternative to these track circuits to eliminate the occurrence of false red signal overruns.
Train DetectionSpain

Three-rail Castellbisbal

The dual-gauge system of the Spanish railway network is quite challenging in terms of track vacancy detection: Wheel sensors must be installed on two rails next to each other in tight spaces and have to detect axles reliably on the respective rail. Frauscher developed a solution which copes also with the complexity of different interlocking technology in the stations along the line.
Data TransmissionUnited Kingdom of Great Britain and Northern Ireland

Headbolt Lane to Rainford Project

As part of the project to expand Merseyrail services, the operator needed to address the challenge of transmitting indication information over a specific section, spanning from Headbolt Lane to Rainford. In this instance, Frauscher’s technology was utilised to fulfill the data transmission requirements of this project, avoiding expensive and time consuming cabling that would have otherwise been required.